Data centers and supply
Nevada's data center boom could need about 34,000 acre-feet of water a year, most of it at power plants
An updated Desert Research Institute study puts direct cooling demand near 12,800 acre-feet a year by 2036. The water consumed to generate their electricity is far larger.
The Desert Research Institute has revised its January estimate of what data centers will mean for water in Nevada, the driest state. The update uses NV Energy's 2026 planning forecast, which lists 39 proposed high load data centers requesting 16,530 megawatts by 2036. The January study covered 12 projects and about 5,900 megawatts.
At the midpoint of its scenarios, the institute estimates direct cooling use of about 12,770 acre-feet a year, roughly 4 billion gallons, plus about 21,283 acre-feet consumed at the utility level to generate the power. Data centers are about 5% of NV Energy's sales today and are expected to reach 64% by 2046, according to the Nevada Independent.
The supply question is where the business case sits. The report says new growth will largely come from unappropriated groundwater, water reclamation or water transfers, and that direct demand will depend on cooling technology, with direct to chip and immersion systems among the more efficient options. A closed loop 100 megawatt facility in Las Vegas used less than 2 acre-feet in 2025, while an evaporative Google site in Henderson used about 636 acre-feet in 2024.
Sources: Facilities Dive; The Nevada Independent; Desert Research Institute, January report